News

News

October

2018

Terrafame’s net sales in the third quarter totalled EUR 86.0 million – positive EBITDA, operating result and cash flow

25.10.2018

Key figures in July−September 2018 (Q3 2017 reference period in parentheses) 7,326 tonnes of nickel (5,506) and 16,530 tonnes of zinc (12,242) were produced. Net sales totalled EUR 86.0 million (63.9). EBITDA was EUR 12.9 million (47.6). EBI...

Read more

Publishing of third quarter 2018 interim report on 25 October

2.10.2018

Terrafame Ltd will publish its third quarter interim report on Thursday, 25 October at about 1pm on the company website. The press conference covering the interim report as well as the battery chemicals plant project will be held in Helsinki, Finland. ...

Read more

July

2018

Terrafame’s net sales in H1 totalled EUR 162.4 million – positive EBITDA and operating result

27.7.2018

Key figures in January−June 2018 (H1 2017 reference period in parentheses) 12,341 tonnes of nickel (9,963) and 29,104 tonnes of zinc (20,995) were produced. Net sales totalled EUR 162.4 million (88.5). EBITDA was EUR 20.9 million (-51.3). EBI...

Read more

June

2018

Publishing of first half 2018 financial report on 27 July

18.6.2018

Terrafame Ltd will publish the first half financial report on Friday, 27 July 2018 at about 10am EET on the company website. The press conference for media will be held at Terrafame in Sotkamo, Finland. Invitation to the media will be sent in the week ...

Read more

May

2018

Terrafame’s net sales continued to grow – EBITDA of first quarter totalled EUR 9.8 million

2.5.2018

Key figures in January−March 2018 (Q1 2017 reference period in parentheses) 6,421 tonnes of nickel (4,787) and 15,008 tonnes of zinc (9,791) were produced. Net sales totalled EUR 85.7 million (41.3). EBITDA was EUR 9.8 million (-18.4). EBITDA...

Read more

April

2018

Publication of first quarter 2018 interim report on 2 May 2018

19.4.2018

Terrafame Ltd will publish its first quarter interim report on Wednesday, 2 May 2018 at about 1pm EET on the company’s website. The press conference for media will be held in Sotkamo, Finland. Invitation to the media will be sent in the previous week. ...

Read more

January

2018

Terrafame’s net sales more than doubled in 2017 – EBITDA positive

24.1.2018

Key figures in January−December 2017 (2016 reference period in parentheses) 46,200 tonnes of nickel (37,042) and 91,827 tonnes of zinc (70,299) were stacked on the primary heap. 20,864 tonnes of nickel (9,554) and 47,205 tonnes of zinc (22,575) w...

Read more

Publication of fourth quarter 2017 interim report on 24 January

16.1.2018

Terrafame Ltd. will publish its fourth quarter interim report on Wednesday, 24 January at about 10 am EET on the company’s website. The press conference for media will be held in Helsinki. Invitation to the media will be sent in the week of publication. ...

Read more

October

2017

Terrafame’s third quarter net sales totalled EUR 63.9 million – profitability improved clearly

25.10.2017

Key figures in July−September 2017 (Q2 2017 reference period in parentheses) 13,192 tonnes of nickel (11,038) and 25,697 tonnes of zinc (23,149) were stacked on the primary heap. 7,197 tonnes of nickel (5,361) and 13,027 tonnes of zinc (12,657) w...

Read more

Publication of third quarter 2017 interim report on 25 October

16.10.2017

Terrafame Ltd. will publish its third quarter interim report on Wednesday, 25 October at about 10 am on the company’s website. The press conference for media will be held in Helsinki this time. Invitation to the media will be sent in the week of publicati...

Read more

July

2017

Terrafame’s nickel production in H1 exceeded the production volume of the whole previous year − Net sales totalled EUR 88.5 million

28.7.2017

Key figures in January−June 2017 (H1 2016 reference period in parentheses) 21,108 tonnes of nickel (14,391) and 43,388 tonnes of zinc (27,543) were stacked on the primary heap. 10,447 tonnes of nickel (3,653) and 23,037 tonnes of zinc (8,451) wer...

Read more

Publication of second quarter 2017 interim report on 28 July

18.7.2017

Terrafame Ltd. will publish its second quarter interim report on Friday, 28 July at about 10 am on the company’s website. The press conference for media will be held in Helsinki this time. Invitation to the media will be sent earlier in the week of public...

Read more

April

2017

Terrafame produced a record amount of nickel in the first quarter − net sales EUR 41.3 million

27.4.2017

Key figures in January−March 2017 10,070 tonnes of nickel (Q4 2016: 11,757) and 20,239 tonnes of zinc (Q4 2016: 22,144) were stacked on the primary heap. 5,086 tonnes of nickel (Q4 2016: 4,885) and 10,380 tonnes of zinc (Q4 2016: 10,697) were leac...

Read more

January

2017

Terrafame’s EBITDA positive in the fourth quarter of 2016 – Full-year net sales exceeded EUR 100 million

19.1.2017

Key figures in January−December 2016 14.2 million tonnes of ore was stacked on the primary leaching heaps. 11,584 tonnes of nickel and 27,868 tonnes of zinc were leached. 9,554 tonnes of nickel and 22,575 tonnes of zinc were produced. Net sale...

Read more

November

2016

Terrafame: the prerequisites for profitable mining operations strengthened significantly in the third quarter

7.11.2016

Ramp-up and operations of the mine in brief: In July–September 2016, the ramp-up and operations of the Terrafame mine continued to proceed according to plans. The most central production goals were met and costs were below budget in the third quarter. ...

Read more

July

2016

The ramp-up performance of the Terrafame mine improved as planned in the second quarter

27.7.2016

Ramp-up and operations of the mine in brief: In January–June 2016, the ramp-up and operations of the Terrafame mine proceeded according to plans. Production goals were met and costs were below budget in the second quarter. In addition, occupational saf...

Read more

May

2016

The ramp-up of the Terrafame mine continued strong in April

19.5.2016

The ramp-up of the Terrafame mine proceeded according to plans throughout the early 2016. The ramp-up progressed in line with the key targets set for the ramp-up also in April.   The amount of ore stacked on the primary heaps in January–April tot...

Read more

April

2016

The ramp-up of the Terrafame mine continued according to plan in early 2016

14.4.2016

Ramp-up and operations of the mine in brief:   The ramp-up of the Terrafame mine proceeded in 2015 and in January–March 2016 in accordance with the set targets. The amount of ore stacked on the primary heap in January–March totalled 2.7 million...

Read more